What is a WIR in construction?

What a Work Inspection Request means, what goes into the WIR format, how to prepare one step by step, and how a WIR differs from a MIR.

Short answer: a WIR (Work Inspection Request) is a form the contractor sends to the consultant to ask for an inspection of completed work before the next activity can start. For example, rebar must be inspected and approved before concrete is poured. The consultant inspects the work on site and returns the WIR with a status such as approved, approved with comments, or rejected.

WIR meaning and why it matters

WIR stands for Work Inspection Request. Depending on the project, you may also see it called an Inspection Request (IR), a Request for Inspection, or a WIR/IR. They all mean the same thing: a formal, numbered request from the contractor asking the consultant (the engineer's representative) to come and inspect a piece of work.

Many activities on a construction site get covered up by the next activity. Rebar disappears inside concrete, pipes are hidden behind walls, and waterproofing goes under screed. Once they're covered, nobody can check them. The WIR makes sure the work is inspected and accepted while it can still be seen and corrected.

For the contractor, an approved WIR is also evidence. It proves the work was inspected and accepted on a certain date. That matters for interim payments, for handover, and for any dispute later.

How the WIR process works

The details change from project to project, but the flow is almost always the same:

  1. Approved documents first. The method statement, Inspection and Test Plan (ITP), shop drawings and materials for the activity are already approved.
  2. Work is completed. The site team finishes the activity, or a defined part of it, such as one slab pour area or one floor of blockwork.
  3. Internal check. The contractor's own QA/QC engineer checks the work against the ITP checklist before anyone calls the consultant.
  4. WIR is raised and submitted. The form is filled in, numbered, signed and submitted with its attachments. This must be done within the notice period, often 24 hours before the inspection.
  5. Joint inspection on site. The consultant's inspector checks the work, often together with the contractor's engineer.
  6. Status returned. The consultant writes the result and any comments on the WIR and returns it.
  7. Next activity or rework. If approved, the next activity can start. If rejected, the defects are corrected and a new or revised WIR is submitted.

Hold points: in the ITP, some inspections are marked as hold points. Work must stop until that inspection is approved. Others are witness points: the consultant is invited, but work may continue if they don't attend. A WIR is mandatory for every hold point.

What a WIR format contains

Every consultant has their own layout, but almost every WIR format has the same building blocks:

WORK INSPECTION REQUESTWIR No. PRJ-WIR-B2-0147
Project
Project: Residential TowerContract No.: C-2041Contractor: ABC ContractingConsultant: XYZ Engineers
Work details
Discipline: Civil / StructuralActivity: Rebar for slabLocation: Building 2, Level 5Drawing: S-B2-L05-101 Rev CITP ref.: ITP-CIV-004Method statement: MS-CIV-012
Inspection
Date: 22-Oct-2026Time: 09:00
Attachments
Marked-up drawingITP checklistSurvey reportPhotos
Consultant's result
A – ApprovedB – Approved with commentsC – Revise & resubmitD – Rejected
Signatures
Contractor QA/QCConsultant inspector
A typical WIR layout. Your consultant's form may differ, but the same information is almost always required.
SectionWhat to fill in
WIR numberA unique number following the project's numbering system, for example PRJ-WIR-B2-0147 (project, document type, building, serial).
Project detailsProject name, contract number, contractor and consultant.
Discipline & activityCivil, architectural, MEP and so on, plus the exact activity, for example "Rebar for slab".
LocationBuilding, level, zone, grid lines or room, specific enough that the inspector goes straight to the right place.
ReferencesApproved drawing number and revision, ITP number, method statement and material approvals used.
Inspection date & timeWhen the work will be ready, respecting the notice period.
AttachmentsDrawing with the inspected area highlighted, filled-in ITP checklist, survey or test results, and photos if required.
Result & commentsCompleted by the consultant: status code, comments, name, signature and date.

How to prepare a WIR, step by step

  1. Check that the documents are approved. The shop drawing, method statement and materials must all be approved. A WIR that refers to an unapproved drawing will be rejected.
  2. Do your own inspection first. Walk the area with the ITP checklist and fix the defects before you raise the WIR, not after the consultant finds them.
  3. Take the next number. Use the next serial number in the WIR register for that building or discipline. Never reuse a number, even if a WIR was cancelled.
  4. Describe the work precisely. Give the exact activity and location. "Blockwork, Level 3" is too vague. "Blockwork, Level 3, Apartments 301–304, grid A–D / 1–4" is clear.
  5. Reference the latest approved revision. Quote the drawing revision that was actually used on site.
  6. Mark up the drawing. Highlight the inspected area so there is no doubt about what the WIR covers.
  7. Attach the supporting documents that the ITP asks for: checklists, test reports, survey results, and the delivery notes or MIR for the materials used.
  8. Sign, submit and log it. Submit within the notice period and record it in the WIR register, with the submission date, status and the date it came back.

WIR status codes

Consultants return each WIR with a status. The exact letters and wording are set in each project's specification, but a common pattern is:

CodeTypical meaningWhat to do next
AApprovedProceed with the next activity.
BApproved with commentsProceed, but address the comments.
CRevise and resubmitCorrect the work or the documents and submit again.
DRejectedDo not proceed. Rectify the work and raise a new inspection.

Always follow the code definitions in your own project's quality plan. Some projects use only three codes, and some use numbers instead of letters.

WIR vs MIR: the difference

The two are often confused because they look alike and travel together. The simple rule is: a MIR checks materials, and a WIR checks work.

WIR – Work Inspection RequestMIR – Material Inspection Request
What is inspectedCompleted work on site (installation, workmanship)Materials delivered to site
WhenAfter the work is done, before it is covered or the next activity startsAfter delivery, before the material is used
Checked againstApproved shop drawings, ITP and method statementApproved material submittal (MAR), specification and delivery documents
Typical attachmentsMarked-up drawing, ITP checklist, test and survey resultsDelivery note, mill or test certificates, MAR approval
ExampleRebar fixing for a slab before concreteSteel bars arriving on site before fixing

The order on site is usually MAR → MIR → WIR. First the material is approved on paper (MAR), then the delivery is inspected (MIR), and finally the installed work is inspected (WIR).

Common mistakes that get a WIR rejected

  • The work wasn't actually ready when the inspector arrived.
  • The drawing referenced is an old or unapproved revision.
  • The location is vague, or the WIR covers a different area from the one offered on site.
  • The ITP checklist, test results or MIR for the materials used are missing.
  • The WIR was submitted without the required notice period.
  • Wrong or duplicate WIR number, so the register no longer matches.

Most rejections are paperwork problems, not workmanship problems, which makes them easy to avoid with a consistent process.

Free WIR template: a clean, ready-to-use WIR format in Word, Excel and PDF is coming soon to our free templates library. No sign-up needed.

FAQ

What is the full form of WIR in construction?

WIR stands for Work Inspection Request. Some projects call it an Inspection Request (IR) or a Request for Inspection.

Who prepares a WIR?

The contractor prepares the WIR, usually the site engineer for the activity together with the QA/QC engineer, and the document controller submits it. The consultant or engineer's representative inspects and returns it with a status.

How much notice is needed before a WIR inspection?

It depends on the contract and the project quality plan. Many projects ask for 24 hours' notice, and some ask for 48 hours for major activities such as concrete pours. Always check your project's specification.

What is the difference between a WIR and a MIR?

A WIR asks the consultant to inspect completed work, such as rebar fixing or blockwork, before the next activity starts. A MIR asks the consultant to inspect materials delivered to site, checking that they match the approved material submittal (MAR).

Is a WIR the same as an RFI?

Usually not. An RFI is normally a Request for Information, a question to the designer or consultant. However, on some projects RFI means Request for Inspection, which is the same thing as a WIR. Check your project's document numbering procedure.

Prepare WIRs in minutes

Stop filling WIR forms by hand

ADoc Flow fills your consultant's own WIR form, gives it the next number, highlights the drawing, attaches the ITP page and keeps the WIR register up to date automatically.

ADoc Flow preparing a work inspection request automatically