Rebar inspection checklist: what to check before concrete

A practical reinforcement inspection checklist for QC engineers: documents, bar sizes and spacing, laps, cover, fixing and cleanliness, plus a rebar weight calculator and the mistakes that get rebar WIRs rejected.

Rebar inspection checklist: what to check before concrete

Short answer: before concrete is poured, the reinforcement is inspected against the approved shop drawing: bar sizes and numbers, spacing, laps and their location, anchorage and bends, concrete cover and cover blocks, chairs and fixing, starter bars, embedded items, and cleanliness. It is a hold point in almost every ITP, so the pour cannot start until the rebar WIR is approved.

Before you inspect: documents

  • Approved shop drawing / bar bending schedule at the latest revision (code A or B, comments applied).
  • Approved MAR for the reinforcement, and the MIR for the delivered batch with mill certificates matching the heat numbers on the bars.
  • Lab test results for the rebar samples (tensile, bend, mass) at the frequency in the specification.
  • The ITP for concrete works and the approved method statement.

The rebar inspection checklist

CheckWhat to look for
Bar size and gradeDiameter and grade as per drawing; check markings on the bars.
Number and spacingCount bars between grids; measure spacing in several places. Top and bottom layers both.
LapsLap length as shown on the drawing; laps staggered and not in zones the designer prohibits.
Anchorage and bendsHooks, bend diameters and development lengths as detailed.
CoverCover blocks of the right size and material, at the right spacing, on all faces.
Chairs and spacersTop mesh supported so it does not sag when walked on.
Stirrups and linksSize, spacing (especially at beam ends and column zones), hook angle.
Starter bars and dowelsCorrect position, length and number for the next lift.
Openings and embedded itemsTrimmer bars around openings; sleeves and MEP items coordinated.
Tying and stabilityCage is rigid and will not move during the pour.
CleanlinessNo mud, oil, release agent or loose rust on bars; formwork free of debris and tie wire.

Rebar is usually inspected together with formwork on one pre-pour WIR. Use our pre-pour checklist and the free concrete pour card template to sign off every discipline.

Concrete cover: the most common failure

Cover protects the steel from corrosion and fire. Too little cover is one of the most frequent rebar NCRs, and it is invisible once concrete is poured. Always take the required cover from the structural drawings and specification. For example, ACI 318 requires 75 mm for concrete cast against and permanently exposed to earth; elements exposed to weather or aggressive soils, common on Gulf sites, often need more.

Tip: measure cover at the most congested points (beam-column joints, laps, around openings), not just in open areas. Check that cover blocks are the specified type: concrete or approved plastic, not stones or timber.

Rebar weight calculator

Quick check of quantities against the bar bending schedule or a delivery: the weight of steel bar is approximately d² ÷ 162 kg per metre, where d is the diameter in mm.

BarT8T10T12T16T20T25T32
kg/m0.3950.6170.8881.5782.4663.8536.313

Mistakes that get rebar WIRs rejected

  1. Inspecting against an old shop drawing revision.
  2. Missing or wrong cover blocks, especially on vertical faces.
  3. Laps in the wrong zone or too short.
  4. Bars missing around openings or at beam ends.
  5. Mill certificates that do not match the heat numbers delivered.
  6. Cage dirty with mud or oil, or debris left in the formwork.

If the problem is found after the pour, it becomes an NCR and usually needs investigation. That is why rebar is a hold point.

FAQ

What do you check in a rebar inspection?

Bar size and grade, number and spacing, laps, anchorage and bends, cover and cover blocks, chairs, stirrups, starter bars, openings and embedded items, tying and cleanliness, all against the approved shop drawing.

How do you calculate rebar weight per metre?

Weight in kg per metre is approximately the diameter in mm squared divided by 162. For example a 16 mm bar weighs about 1.58 kg/m.

Is rebar inspection a hold point?

In almost every ITP, yes. Concrete must not be poured until the rebar (and usually formwork) WIR is approved.

What is the minimum concrete cover?

It depends on the element and exposure, and is set by the structural drawings and specification. As one example, ACI 318 requires 75 mm for concrete cast against earth.

Prepare QA/QC documents in minutes

Stop filling forms by hand

ADoc Flow fills your consultant's own WIR, MAR and MIR forms, numbers them, highlights the drawing, attaches the ITP and keeps every register up to date automatically.

ADoc Flow preparing a work inspection request automatically